Complete
Basin and channel
A 4.5-hectare marina basin at 10 metres LAT, a 50-metre entrance and a 5-metre LAT access channel.

Current status
The basin and access channel are complete, the wider marine development is approved, and initial maintenance and repair operations began in 2025.
At August 2026
Complete
A 4.5-hectare marina basin at 10 metres LAT, a 50-metre entrance and a 5-metre LAT access channel.
Approved
Four trade-specific sheds totalling about 20,000 square metres and 3 hectares of hardstand, with further land reserved.
Operating
Maintenance, repair and overhaul operations began in 2025, creating real vessel and customer experience ahead of the full build.
Early operations
ECMC recorded five vessel requests accepted and three unable to be accommodated in 2025. In the first half of 2026, four were accepted and two could not be accommodated. These early figures are modest, but they show both operational activity and the current limitations of an incomplete facility.
Vessel counts are management information supplied for the project and are not a forecast of future demand or revenue.

Read the status correctly
The deep-water basin, entrance and access channel, together with enabling site works.
Early maintenance, repair and overhaul activity within the capability currently available.
The main yard, workshop and hardstand development described in the planning approvals.
The full heavy-lift and servicing configuration that completes the marine precinct.